Timeline

2026
- March
- Bond vote passes
- Engage with the State to secure funding
- March
2027
- Governor’s Budget
- Capital Committee review
- May
- Update construction estimates, balance the scope & budget
- July
- State budget is finalized
- Bond local funds
- Full design/engineering and bid documents
- Bidding and mobilize
2028
- Restaurant addition and renovation
- Summer renovations
- Graphic Design
- Business
- Culinary kitchen
- Fall renovations
- Video Production
- Construction & Trades
2029
- Spring renovations
- Health Science
- Powersports
- Summer renovations
- Welding/Machining
- Electrical Engineering
- Career Center
- Fall
- Punchlist and closeout
- December
- All programs are complete
- Spring renovations